Request for Proposal (RFP) 2025-24 Ross Cage Hoist Rope Replacement

Contract Schedule Milestone Date
Registration Deadline for Site Visit, 1600
Optional Site Visit, 1000 - 1200
Questions Submitted, 1600
Questions and Answers Posted, 1600
RFP Responses Due, 1600

Summary

This RFP is issued by the SDSTA for Maintenance Services to replace the wire rope on the Ross Cage Hoist overwind drum. An individual firm will be selected for a fixed price contract based on the total costs, technical acceptability, and meet the project schedule based on the Scope of Work (SOW).